CLT Beyond — Charlotte Douglas Airport Capital Program
Charlotte Douglas International Airport proposes CLT Beyond, a capital program estimated at more than $2.1 billion. It is tied to a proposed airline agreement that remains subject to Charlotte City Council approval.
At a glance
- Status
- Under reviewProposed airline agreement and capital program under review; individual projects have separate approval and delivery steps.
- Location
- Charlotte Douglas International Airport, Charlotte, Mecklenburg County, NC
- Last verified
Key figures
- Proposed capital program
- More than $2,100 millionProposed estimateMore than this amount in the proposed multi-project program; not an approved construction contract.
- Proposed agreement term
- 10.5 yearsProposedProposed agreement term, subject to City Council approval.
- Estimated airline payments
- About $3,000 millionEstimatedAirport estimate over the proposed base term; not realized revenue or a project budget.
What is documented
The airport presented the proposed 10.5-year Airline Use and Lease Agreement to City Council on October 12, 2026. If approved, its base term would begin January 1, 2027.
CLT Beyond includes nearly a dozen terminal, airfield, electrical and other airport-infrastructure projects. The airport estimates approximately $3 billion in net airline rents, fees and charges over the proposed base term; that estimate is separate from the capital-program cost.
A special Council meeting on the review schedule is listed for October 19. Final approval and its timing remain unresolved.
What to watch next
- The October 19, 2026 special Council meeting and subsequent final action on the airline agreement.
- Component-project consultation and approvals, procurement, permits and delivery schedules.
Program review does not establish that every component is construction-ready. Individual costs and schedules may change, and each project has its own delivery steps.
Sources
- Primary sourceCharlotte Douglas International Airport — Update on proposed Airline Use and Lease AgreementPublication date not provided
- Primary sourceCharlotte Douglas International Airport — Draft airline agreement presentation — October 12, 2026Publication date not provided