GROWTH TRACKER

Find a project.

Explore development and infrastructure projects by place, topic and current status. Open a record for its sources, latest developments and what to watch next.

Includes Mooresville projects and the Catawba River bridge replacement. Cadia Village and its Lowes Foods component are linked records, not separate development investments.

46 project records

Manufacturing & industrial · Economic investmentProposed

Corvid Technologies Mooresville Advanced Manufacturing Expansion

On November 17, 2026, Corvid Technologies announced the purchase of a separate 160,000-square-foot existing manufacturing facility in Mooresville, minutes from its headquarters. The acquired facility’s address, purchase price, recorded deed and operating timeline have not been independently confirmed. Corvid plans a 400,000-square-foot advanced manufacturing expansion at its Mooresville campus. Iredell County approved a performance-based grant of up to $3,187,100 on October 20; Mooresville’s October 19 approval is reported. The state announced $95 million and 423 planned jobs; local materials cite up to $98 million and a 170-job minimum. Construction and actual hiring remain unconfirmed.

Status evidence: October 20, 2026Announcement; commencement unverified · Iredell CountyChecked November 17, 2026

Open question: Construction schedule, permits, site work and commencement have not been confirmed.

Manufacturing & industrial · Economic investmentApproved

Global Emission Systems — Troutman Headquarters (Project Speed)

Global Emission Systems plans a headquarters, R&D and advanced-manufacturing facility in Troutman. Iredell County approved up to $474,217 over five years on November 17 for up to $34.68 million in taxable investment, at least 40 new jobs and retention of 10 positions. Construction and actual hiring are not confirmed.

Status evidence: November 17, 2026Documented by · Iredell CountyChecked November 21, 2026

Open question: The investment, jobs and approximately 135,000-square-foot facility are planned, not completed. The exact parcel, executed agreements, permits, utility commitments, construction and realized hiring remain unverified. No project-specific utility constraint is established.

Manufacturing & industrial · Utilities · Economic investmentProposed

LIMiK Capital Transformer Manufacturing — Gaffney

LIMiK Capital plans a $327.7 million transformer-manufacturing facility at 34 Commerce Drive in Gaffney, Cherokee County, with 400 planned jobs. South Carolina announced the project November 17; operations are expected in early 2028, while construction and actual hiring are not confirmed.

Status evidence: November 17, 2026Documented by · South Carolina Department of CommerceChecked November 21, 2026

Open question: The investment and jobs are planned. Approved job-development credits do not establish construction, production or completed hiring. Customer contracts, production volumes and permit completion remain unverified.

Manufacturing & industrial · Economic investmentApproved

Speedball Art Products Statesville Expansion

Iredell County approved up to $120,253 over five years for Speedball’s planned Statesville expansion on November 17, following the city’s separate November 16 incentive approval. County materials use $10 million and 25 planned jobs; city materials use approximately $8 million and at least 12. Lease commencement, facility work and hiring remain unconfirmed.

Status evidence: November 17, 2026Documented by · Iredell CountyChecked November 21, 2026

Open question: City and county investment and job figures differ and are not combined. The reuse-grant application is not a grant award. Executed agreements, lease commencement, renovations, equipment installation, opening and actual hiring remain unverified.

TransportationFunded

ACWR Piedmont Division Freight-Rail Improvements

NCDOT announced two ACWR Piedmont Division rail awards covering Mecklenburg, Montgomery and Stanly counties on November 16. The $2,499,836 total combines separate track/switch and bridge contributions; project-specific construction timing is not confirmed.

Status evidence: November 16, 2026Documented by · NCDOT Rail DivisionChecked November 21, 2026

Open question: These are two NCDOT contributions, not one construction contract or a complete project cost. Exact mileposts, agreements, local matches and construction dates remain unverified. Statewide program jobs or investment totals are not attributed to ACWR.

Manufacturing & industrial · Land useProposed

AirBox Statesville Expansion — Peachtree Road

Statesville City Council denied a general B-5 rezoning request for AirBox’s proposed expansion near Peachtree Road and Maple Care Lane on November 16. The 7–1 vote concerns roughly 10.4 acres; a revised application, alternative site or cancellation has not been verified.

Status evidence: November 16, 2026Announcement; commencement unverified · City of StatesvilleChecked November 21, 2026

Open question: The denial applies to this rezoning request. It does not establish cancellation of the company’s expansion. No revised filing, alternative site, permit or construction start has been verified.

Data Center & Digital Infrastructure · Utilities · Policy & planningApproved

Duke Energy NC Data-Center Large-Load Rate Schedule

North Carolina regulators approved a modified data-center rate schedule in November 16 orders for Duke Energy Carolinas and Duke Energy Progress, according to the companies’ SEC-filed summaries. The schedule addresses large-load contracts and grid-cost protections; final tariff sheets and implementation remain unverified.

Status evidence: November 16, 2026Documented by · Duke Energy, filed with the SECChecked November 21, 2026

Open question: The cited SEC exhibits are company summaries of NCUC orders; the signed orders were not accessible at review. The modified schedule should not be treated as the October settlement unchanged. Residential base-rate changes are separate, and neither elimination of all cost shifting nor guaranteed savings is established.

TransportationUnder review

I-77 South Express Lanes and Community Benefits

Charlotte’s I-77 South Express Lanes project remains in planning and design along the roughly 11-mile corridor from the South Carolina line to I-277/N.C. 16. City Council approved an advisory community-benefits working group on November 16, according to WFAE reporting; individual benefit projects and highway construction remain unconfirmed.

Status evidence: November 16, 2026Announcement; commencement unverified · NCDOTChecked November 21, 2026

Open question: The city agenda’s final-action field remained blank at review; adoption is attributed to contemporary reporting. Final membership, signed governance, design, funding execution and construction timing remain unresolved. The $300 million is not a list of awarded construction projects.

Critical minerals · Manufacturing & industrial · Economic investmentUnder review

Carolina Lithium — Gaston County

Carolina Lithium in Gaston County received its final state air quality permit on November 13, 2026, following the mining permit issued in 2024. The overall project remains under review: local zoning compliance and other implementation steps remain, and construction has not been confirmed.

Status evidence: November 13, 2026Announcement; commencement unverified · NC Department of Environmental QualityChecked November 15, 2026

Open question: Applicable local zoning compliance remains required before construction and operation.

Utilities · Land useUnder review

Piedmont Natural Gas Salisbury Energy Reliability Center

Piedmont Natural Gas proposes a compressor station on Young Road in unincorporated Rowan County near Salisbury. At the applicant’s request, the county removed its November 16 rezoning hearing from the agenda to allow more time to address neighbors’ concerns.

Status evidence: November 12, 2026Documented by · Rowan CountyChecked November 15, 2026

Open question: Consideration is delayed, not cancelled; no replacement hearing date is established. Rezoning, required permits, construction and operation are not confirmed. County staff and applicant narrative give different parent-parcel acreages; 26.8 acres describes the requested project portion.

Data Center & Digital Infrastructure · Policy & planningApproved

Rowan County Data-Center Moratorium and Permanent Standards

Rowan County’s data-center moratorium applies in its planning jurisdiction in unincorporated Rowan County, not across every municipality in the county. The temporary measure runs May 4, 2026 through May 4, 2027; permanent standards remain under review. A November 12 staff memo outlines the study process for a November 23 Planning Board discussion.

Status evidence: May 4, 2026Documented by · Rowan County Planning & DevelopmentChecked November 20, 2026

Open question: The moratorium is temporary. Permanent ordinance text, final limits and an adoption schedule have not been verified. It is not a blanket ban in every Rowan County municipality.

Land use · Housing · OtherUnder review

Paddock Properties / Mooresville Motorsports Community

In unincorporated Rowan County near Mooresville, Paddock Properties seeks conditional rezoning for a 257.21-acre private motorsports and residential complex around the existing Mooresville Dragstrip. The new proposal and additional watershed allocation remain under review; construction of the new complex has not been confirmed.

Status evidence: November 9, 2026Documented by · Rowan County Planning & DevelopmentChecked November 20, 2026

Open question: The new complex is an applicant proposal. Earlier partial approvals and existing dragstrip operations do not establish approval or construction of this buildout.

Housing · Land useApproved

Moose Club Road — Novel Holdings Subdivision, Statesville

Statesville City Council approved the second readings of the Novel Holdings Moose Club Road rezoning and annexation in Iredell County on November 2, 2026, each by a 5–3 vote. The Iredell County development allows up to 48 detached homes on approximately 19 acres. Rezoning became effective November 2; annexation takes effect November 30. Construction has not been confirmed.

Status evidence: November 2, 2026Documented by · City of StatesvilleChecked November 5, 2026

Open question: Final subdivision and infrastructure approvals, permits, builder and construction commencement have not been established.

Utilities · Manufacturing & industrial · HousingUnder construction

Third Creek Sewer Extension — Stamey Road corridor

The City of Statesville confirms that construction on the Third Creek Sewer Extension began October 19, 2026. Its November 2 council update reports ongoing work, while a city notice schedules rock blasting to begin November 4. The roughly 9,600-foot extension serves the Third Creek / Stamey Road corridor; current completion timing remains unconfirmed.

Status evidence: November 2, 2026Documented by · City of StatesvilleChecked November 5, 2026

Open question: The current completion date remains unconfirmed and may change.

Economic investmentProposed

The Clearing House Charlotte Expansion

The Clearing House announced an $11.5 million Charlotte expansion with 200 planned jobs and an announced average annual salary of $162,322. Performance-based state JDIG incentives were approved October 27, 2026. The exact office location, opening date and actual hiring have not been confirmed.

Status evidence: October 27, 2026Announcement; commencement unverified · North Carolina Department of CommerceChecked October 28, 2026

Open question: The exact Charlotte office location has not been announced in the reviewed source.

Data Center & Digital Infrastructure · Policy & planningApproved

Charlotte Telecommunications and Data Storage Facilities Moratorium

Charlotte City Council approved an extension of the temporary moratorium on new telecommunications and data storage facility applications on October 26, 2026. The moratorium was originally due to expire November 5, 2026 and is extended to no later than October 18, 2027. Existing facilities and legally exempt or previously approved projects are not halted by this measure. The policy gives the city time to evaluate potential land-use and infrastructure standards; it is not a construction permit decision for any particular data center.

Status evidence: October 26, 2026Documented by · City of CharlotteChecked November 3, 2026

Open question: Permanent regulations and their adoption timing are not yet established.

Data Center & Digital Infrastructure · Economic investmentApproved

Digital Realty CLT13 — Moores Chapel

Digital Realty’s CLT13 campus in the Charlotte mailing area of Mecklenburg County has an approved rezoning and a draft county air permit for emergency generators. Final air-permit action, construction commencement and operations are not established by the primary documents used here.

Status evidence: May 19, 2025Documented by · Mecklenburg County Air QualityChecked November 15, 2026

Open question: Rezoning approval is not final air-permit approval or confirmation of construction. The draft’s 726 MW of backup generation is distinct from the proposed 400 MW IT load. Municipal boundary and current construction progress require separate confirmation.

Manufacturing & industrial · Economic investmentClosure announced

Toter — Statesville Facility Closures

Toter filed a permanent-closure notice for two Statesville facilities on October 23, 2026. North Carolina’s WARN summary lists 96 affected employees in total and a December 22, 2026 effective date.

Status evidence: October 23, 2026Documented by · North Carolina Department of CommerceChecked November 2, 2026

Open question: Announced closure; completion and actual separations have not been verified.

Manufacturing & industrial · Economic investment · Data Center & Digital InfrastructureProposed

US Conec — Hickory Advanced Optical Interconnect Manufacturing Expansion

US Conec announced a $149.7 million expansion of its Hickory optical-interconnect manufacturing operations, with 224 planned additional jobs and an announced average annual wage of $56,982. Catawba County EDC says the company will equip and fit out a 221,000-square-foot host building currently under construction at Catawba Commerce Center in Fairgrove Business Park, with expansion and hiring targeted by year-end 2030. The state describes a 200,000-square-foot building; building size remains unreconciled. The host building’s construction does not establish commencement of US Conec fit-out, operating production or actual hiring.

Status evidence: October 22, 2026Announcement; commencement unverified · North Carolina Department of CommerceChecked October 29, 2026

Open question: State 200,000-sf versus EDC 221,000-sf building descriptions are unresolved.

Economic investment · Manufacturing & industrialProposed

Carolina Crossing — St. John Properties, Indian Land

St. John Properties announced Carolina Crossing, a planned speculative business community in Indian Land, unincorporated Lancaster County, on a 24-acre site it has acquired near Collins Road and U.S. 521. The initial plan includes two flex/R&D buildings and one single-story office building totaling 87,760 square feet. Groundbreaking is targeted for fall 2026, but construction commencement has not yet been verified.

Status evidence: October 19, 2026Announcement; commencement unverified · St. John Properties, Inc.Checked October 20, 2026

Open question: Groundbreaking has been announced for fall 2026 but has not yet been independently confirmed.

Manufacturing & industrial · Economic investmentClosure announced

FTGU — Conover Facility Closure

FTGU filed a permanent-closure notice for its Conover facility on October 19, 2026. North Carolina’s WARN summary lists 93 affected employees and a December 16, 2026 effective date; WBTV reports December 18. The date difference remains unresolved.

Status evidence: October 19, 2026Documented by · North Carolina Department of CommerceChecked November 2, 2026

Open question: Announced closure; completion and actual separations have not been verified.

Housing · Land useUnder review

The Oaks at James Farm Revision — Statesville

Statesville City Council unanimously approved the first reading of the October 2026 zoning amendment for The Oaks at James Farm. The amendment changes the previously approved 104-townhome plan to a proposal for 57 single-family detached homes on approximately 14.7 acres. The amendment is scheduled for a second reading on November 2, so the revised 57-home plan is not yet finally approved; construction has not been confirmed.

Status evidence: October 19, 2026Documented by · City of StatesvilleChecked October 21, 2026

Open question: Second-reading/final outcome remains pending.

Economic investment · Manufacturing & industrialProposed

Perimeter Group Headquarters Relocation — Charlotte

Perimeter Solutions Inc. announced that it expects to relocate its corporate headquarters from Clayton, Missouri, to Charlotte on November 4, 2026, when the company also plans to change its name to Perimeter Group Inc. The company now comprises six businesses across Fire Safety and Specialty Products. Charlotte-based Medical Manufacturing Technologies (MMT), acquired by Perimeter in January 2026, is one of those businesses, but Perimeter has not publicly stated that the MMT acquisition is the reason for the headquarters move.

Status evidence: October 16, 2026Announcement; commencement unverified · Perimeter Solutions, Inc.Checked October 22, 2026

Open question: Exact Charlotte headquarters address has not been announced in the reviewed primary sources.

Healthcare infrastructure · Economic investmentUnder review

Duke Health–CaroMont River District Hospital — Charlotte

Duke Health and CaroMont Health announced that they submitted a Certificate of Need application for a proposed 80-bed hospital in Charlotte's River District. State approval is still pending, and specific services, final site details, construction scope, cost and employment have not yet been established.

Status evidence: October 14, 2026Documented by · Duke HealthChecked October 15, 2026

Open question: Exact parcel/address has not been identified in the reviewed primary announcement.

Healthcare infrastructure · Economic investmentUnder review

Duke Health–CaroMont University City Hospital — Charlotte

Duke Health and CaroMont Health announced that they submitted a Certificate of Need application for a proposed 120-bed hospital in Charlotte's University City area. State approval is still pending, and specific services, final site details, construction scope, cost and employment have not yet been established.

Status evidence: October 14, 2026Documented by · Duke HealthChecked October 15, 2026

Open question: Exact parcel/address has not been identified in the reviewed primary announcement.

Manufacturing & industrial · Economic investmentOperating

Park 4077 — Building 4, Statesville

Iredell EDC reported on October 14, 2026 that NorthPoint Development’s approximately 600,000-square-foot speculative building at Park 4077 in Statesville is now fully leased. A separate 2026 Iredell EDC ribbon-cutting report documented completion of 585,880 square feet and stated that 70% of the building was occupied and operational at that time. The new leasing milestone does not establish full occupancy.

Status evidence: February 2026Documented by · Iredell EDCChecked October 15, 2026

Open question: The October 14 announcement does not identify the final tenant or confirm that all leased space is occupied.

Manufacturing & industrial · Utilities · Economic investmentProposed

Utili-Serve Conover Headquarters & Manufacturing Expansion

North Carolina Commerce announced that Utili-Serve plans to add 105 jobs, expand its Conover headquarters, and construct a new 25,000-square-foot manufacturing facility. Commerce reports more than $24.8 million of investment, while Catawba County EDC reports at least $11 million; the differing investment definitions have not been reconciled. Construction commencement has not been confirmed.

Status evidence: October 14, 2026Announcement; commencement unverified · North Carolina CommerceChecked October 15, 2026

Open question: The $24.8 million-plus state figure and $11 million-plus local EDC figure are materially different and have not been reconciled.

Transportation · Economic investmentUnder review

CLT Beyond — Charlotte Douglas Airport Capital Program

Charlotte Douglas International Airport presented a proposed 10.5-year Airline Use and Lease Agreement to City Council on October 12. Pending Council approval, the agreement would launch CLT Beyond, an estimated $2.1 billion-plus capital development program spanning terminal, airfield, electrical and other airport infrastructure projects.

Status evidence: October 12, 2026Documented by · Charlotte Douglas International AirportChecked October 17, 2026

Open question: Final City Council approval and timing are unresolved.

Other · Economic investmentUnder construction

Firehouse 44 — River District, Charlotte

The City of Charlotte broke ground October 8 on the permanent Firehouse 44 in the River District. The approximately 14,000-square-foot, two-story, three-bay station is a $23.3 million city project; Samet Corp. is design-builder and ADW Architects provides architectural services.

Status evidence: October 8, 2026Documented by · City of CharlotteChecked October 17, 2026

Open question: Final completion/opening date remains to be confirmed from the City.

Data Center & Digital Infrastructure · Economic investmentApproved

Henderson Grove Road Data Center — Salisbury

In Salisbury, City Council adopted the conditional rezoning on October 6, 2026 for the Henderson Grove Road Data Center. Trammell Crow Company is the developer and Flexential is the planned operator/end user. The current project plan is a 296,518-square-foot multi-tenant colocation facility; construction has not been confirmed.

Status evidence: October 6, 2026Documented by · City of SalisburyChecked October 9, 2026

Open question: Construction-document approval, building/trade permits and construction commencement have not been confirmed.

Manufacturing & industrial · Economic investmentProposed

Xingyu Automotive Lighting Systems — Landis, Rowan County

Xingyu Automotive Lighting Systems has publicly announced a planned manufacturing operation in Landis Ridge. A Q1 2026 industrial market report documented a 121,800-square-foot Xingyu Lighting lease at Landis Ridge, and company filings identify a North Carolina manufacturing subsidiary established in January 2026. Announced hiring and operating targets remain future milestones, so the facility is classified conservatively as proposed / leased, pre-operations.

Status evidence: October 6, 2026Announcement; commencement unverified · Charlotte Business JournalChecked October 7, 2026

Open question: Manufacturing fit-out or equipment installation has not been independently verified.

HousingApproved

Havenwood Subdivision — Wall Street, Statesville

Statesville City Council approved the second reading of the Havenwood conditional rezoning by a 4–3 vote. The approval allows residential development on approximately 139 acres formerly zoned Light Industrial. Rezoning approval is not subdivision-plan approval or construction commencement.

Status evidence: October 5, 2026Documented by · City of StatesvilleChecked October 7, 2026

Open question: Final unit mix, construction timing, builders and infrastructure sequencing remain subject to later approvals and implementation.

HousingUnder review

Kingdom Townhomes — 185 Moose Club Road

The Kingdom Townhomes site is in unincorporated Iredell County near Statesville. At the applicant's request, Statesville City Council postponed the proposed rezoning and annexation for Kingdom Townhomes until the February 1, 2027 meeting.

Status evidence: October 5, 2026Documented by · City of StatesvilleChecked October 7, 2026

Open question: Project scope, approval outcome and construction timing remain unresolved.

Manufacturing & industrial · TransportationApproved

Statesville Regional Airport — industrial rezoning and aviation growth node

Statesville City Council unanimously approved the second reading of rezoning request ZC26-10 for approximately 481.5 acres associated with Statesville Regional Airport to Heavy Industrial. The action creates a more uniform industrial zoning framework around an airport where separate aviation investment projects are also advancing.

Status evidence: October 5, 2026Documented by · City of StatesvilleChecked October 7, 2026

Open question: Future industrial users, development timing, infrastructure buildout and parcel-level construction are not established by the rezoning alone.

TransportationUnder construction

Wilkinson Boulevard / U.S. 29–74 Catawba River Bridge Replacement

The Sloans Ferry Bridge / Wilkinson Boulevard U.S. 29–74 crossing replacement and related intersection work between Belmont and Charlotte are under construction. The approximately $78 million award covers the combined B-6051/U-6143 contract.

Status evidence: October 5, 2026Construction reported by · Queen City News / AOLChecked October 17, 2026

Open question: The reported 2032 completion target needs current agency confirmation.

Critical minerals · Policy & planning · Economic investmentApproved

North Carolina Mining Permit Process Changes — SB 445 / SL 2026-59

Section 34 of Session Law 2026-59 (Senate Bill 445) took effect October 1, 2026 for mining permit applications filed on or after that date. It establishes a 10-working-day administrative completeness review, a 60-calendar-day initial technical review, structured subsequent review periods, and a deemed-approval provision if DEQ fails to act as specified after the applicant has submitted all required information. The changes apply statewide to Mining Act permits and are relevant to future lithium and critical-minerals projects, but they are not lithium-specific.

Status evidence: October 1, 2026Documented by · North Carolina General AssemblyChecked October 12, 2026

Open question: Actual effects on permit timing, investment decisions, environmental review, and individual lithium/critical-minerals projects remain to be observed.

TransportationFunded

I-77 / N.C. 73 Interchange Upgrade — Huntersville

NCDOT’s current STIP lists right-of-way in progress for I-5715 and programs construction funding for FY2027. Current permit plans identify an October 20, 2026 letting date. A construction contract award and physical commencement have not yet been verified.

Status evidence: October 2026Announcement; commencement unverified · NCDOTChecked October 17, 2026

Open question: Contract award, final construction amount, notice to proceed and physical commencement are not yet verified.

TransportationUnder construction

N.C. 150 widening: Greenwood Road to U.S. 21

NCDOT documents active widening and bridge work from Greenwood Road in Catawba County across Lake Norman to U.S. 21 in Mooresville. The broader N.C. 150 corridor has separate funding and delivery questions.

Status evidence: October 2026Documented by · NCDOT PublicInputChecked October 6, 2026

Open question: Cost and mileage figures differ between sources; an opening date is not confirmed.

Data Center & Digital Infrastructure · Policy & planningApproved

Statesville telecommunications and data center moratorium

Statesville City Council approved the second reading of a 180-day moratorium on applications for new telecommunications and data centers on September 14, 2026. City follow-up materials describe the moratorium as established; it is a temporary planning measure, not a permanent ban.

Status evidence: September 14, 2026Documented by · City of StatesvilleChecked October 7, 2026

Open question: Future permanent standards and the treatment of any specific pre-existing applications depend on ordinance text and subsequent regulatory actions.

Data Center & Digital Infrastructure · Policy & planningApproved

Kings Mountain Data Center Moratorium

Kings Mountain extended its temporary moratorium on permitting new data centers while the city develops land-use and infrastructure standards. The city currently lists August 24, 2027 as the end date, subject to earlier termination.

Status evidence: August 25, 2026Documented by · City of Kings MountainChecked November 15, 2026

Open question: The city may end the moratorium earlier. Future standards and project-specific exemptions require separate action.

Housing · Retail & mixed useUnder construction

Cadia Village Mooresville

Phased mixed-use development with initial site work underway. Individual buildings and retail components have their own delivery and construction checks.

Status evidence: June 24, 2026Construction reported by · Iredell Free News / Pappas PropertiesChecked October 6, 2026

Open question: Overall site work does not establish construction of every building or the Lowes Foods store.

Retail & mixed useProposed

Lowes Foods at Cadia Village Mooresville

The developer hosts a report announcing a 52,000-square-foot Lowes Foods store with a 2027 opening target. Store construction commencement has not been verified in this check.

Status evidence: July 8, 2026Announcement; store start unverified · Pappas PropertiesChecked October 6, 2026

Open question: Store-specific building permits or construction commencement have not been verified.

TransportationUnder construction

Mooresville East-West Connector: Phase 1

The state program documents Phase 1 under construction. Its route connects Langtree Road with N.C. 115; the future eastern extension is a separate phase.

Status evidence: May 7, 2026Documented by · Town of Mooresville GISChecked October 6, 2026

Open question: Completion and opening targets conflict; a public opening is not confirmed.

TransportationFunded

Talbert Road widening: Brawley School Road to Terrace Road

CRTPO approved $8,795,150 in discretionary funds for this Talbert Road widening segment in Mooresville; its project list gives an approximately $12.5645 million total. The phase schedule is being reconciled. Construction commencement has not been established.

Status evidence: February 18, 2026Documented by · CRTPOChecked October 6, 2026

Open question: The phase schedule is being reconciled. Construction commencement has not been established.

TransportationFunded

I-77 / Cornelius Road interchange (Exit 38)

In northern Mooresville, NCDOT’s January 2026 program includes the Cornelius Road interchange with projected right-of-way and utilities in fiscal 2028, and construction in fiscal 2031.

Status evidence: January 2026Documented by · NCDOTChecked October 6, 2026

Open question: Future phase dates and budget figures need current agency confirmation.

Retail & mixed use · Healthcare infrastructure · Economic investmentApproved

Terrell Town Center — Lowe’s Foods-Anchored Retail & Medical Development

In Terrell, unincorporated Catawba County, catawba County lists MPV Properties’ RZ2025-04 amendment for Terrell Town Center Area 1 as approved by the Board of Commissioners on December 15, 2025. MPV Properties currently markets Terrell Town Center as a fully entitled Lowe’s Foods-anchored retail and medical development at N.C. 150 and Sherrills Ford Road, with retail/medical space targeted for delivery in Q2 2028. Construction commencement has not been independently confirmed.

Status evidence: December 15, 2025Documented by · Catawba CountyChecked October 21, 2026

Open question: Construction commencement, current permit issuance, construction contract status and site-work progress have not been independently verified.