Kings Mountain Data Center Moratorium
Kings Mountain extended its temporary moratorium on permitting new data centers while the city develops land-use and infrastructure standards. The city currently lists August 24, 2027 as the end date, subject to earlier termination.
At a glance
- Status
- ApprovedApproved policy measure; not approval of a data-center facility.
- Location
- Kings Mountain planning jurisdiction, Cleveland and Gaston counties, NC
- Last verified
What is documented
Council adopted Ordinance 26-30 on August 25, 2026 by a 6–1 vote, extending the existing moratorium for twelve months.
The city’s current explanation gives August 24, 2027 as the scheduled end and describes a review of siting, noise, electricity, water, sewer and other impacts.
What to watch next
- Proposed development standards and council votes.
- Any separately adopted exemption, early termination or extension.
The city may end the moratorium earlier. Future standards and project-specific exemptions require separate action.