Rowan County Data-Center Moratorium and Permanent Standards
Rowan County’s data-center moratorium applies in its planning jurisdiction in unincorporated Rowan County, not across every municipality in the county. The temporary measure runs May 4, 2026 through May 4, 2027; permanent standards remain under review. A November 12 staff memo outlines the study process for a November 23 Planning Board discussion.
At a glance
- Status
- ApprovedTemporary moratorium approved; permanent standards under review.
- Location
- Rowan County planning jurisdiction in unincorporated Rowan County, NC; municipal planning jurisdictions are not covered by this county measure.
- Last verified
What is documented
The county’s November 12 memorandum describes a one-year moratorium effective May 4, 2026 through May 4, 2027, covering permitting for new data-center development and expansion, associated rezonings and specified land-development submissions.
The memo specifies exemptions for the Long Ferry Road data-center project and projects qualifying under NCGS 160D-107(c). An exemption is not a new approval for Long Ferry Road.
Staff recommends the full Planning Board develop and review potential ordinance amendments rather than delegating to a subcommittee. November 23 is scheduled for discussion of meeting dates and the study process; the staff recommendation is not an adopted Board decision.
The background packet separates the adopted moratorium from citizen recommendations and model materials. Those recommendations, including possible limits and setbacks, are not adopted permanent county standards.
What to watch next
- November 23, 2026 Planning Board discussion of study process and meeting scheduling.
- County draft ordinance, public hearings and any subsequent adoption; moratorium expiration or amendment.
The moratorium is temporary. Permanent ordinance text, final limits and an adoption schedule have not been verified. It is not a blanket ban in every Rowan County municipality.
Sources
- Primary sourceRowan County Planning & Development — Data Center Text Amendment Considerations — staff memorandum
- Primary sourceRowan County Planning & Development — Data Center Information — adopted moratorium and background proposalsPublication date not provided