Duke Energy NC Data-Center Large-Load Rate Schedule

North Carolina regulators approved a modified data-center rate schedule in November 16 orders for Duke Energy Carolinas and Duke Energy Progress, according to the companies’ SEC-filed summaries. The schedule addresses large-load contracts and grid-cost protections; final tariff sheets and implementation remain unverified.

At a glance

Status
ApprovedModified schedule approved in November 16 orders, as summarized in SEC-filed company disclosures; not verified as implemented.
Location
North Carolina statewide policy within Duke Energy Carolinas and Duke Energy Progress service territories; does not cover their South Carolina customers.
Last verified

What is documented

Duke’s announcement identifies data-center loads above 50 MW. Its order summaries describe a minimum 15-year contract for loads above 100 MW and a 75% minimum billing requirement.

The summaries also describe interim curtailment, upfront contributions for dedicated facilities, transmission letters of credit, early-termination damages and stranded-generation security or charges.

Some transmission cost-allocation and stranded-generation calculations remain to be determined. January 1, 2027 is the expected initial effective date, subject to verification of final tariff implementation.

What to watch next

  • Final approved tariff sheets and actual effective date.
  • Contract/security terms and unresolved cost-allocation methodologies.

The cited SEC exhibits are company summaries of NCUC orders; the signed orders were not accessible at review. The modified schedule should not be treated as the October settlement unchanged. Residential base-rate changes are separate, and neither elimination of all cost shifting nor guaranteed savings is established.