Third Creek Sewer Extension — Stamey Road corridor

Permitted / pre-construction

City project updates report staking and clearing beginning the week of September 14, mobilization planned for October 12, and notice to proceed set for October 19. The City describes the extension as enabling economic development and future commercial and residential growth along the Stamey Road corridor.

At a glance

Status
Permitted / pre-constructionSanitary sewer extension from the Briarwood Subdivision area to the Kennedy Drive Lift Station, including roughly 9,600 feet of new sewer infrastructure serving the Third Creek/Stamey Road area.
Location
Third Creek / Stamey Road corridor, Statesville, Iredell County, NC
What is planned / being built
Sanitary sewer extension from the Briarwood Subdivision area to the Kennedy Drive Lift Station, including roughly 9,600 feet of new sewer infrastructure serving the Third Creek/Stamey Road area.
Latest verified development
City project updates report staking and clearing beginning the week of September 14, mobilization planned for October 12, and notice to proceed set for October 19. The City describes the extension as enabling economic development and future commercial and residential growth along the Stamey Road corridor. [22] [23]Verified fact · Evidence October 6, 2026
What to watch next
October 19 notice to proceed and documented field construction progress
Last checked
October 7, 2026Source review date; not a new construction event.

What this record covers

Sanitary sewer extension from the Briarwood Subdivision area to the Kennedy Drive Lift Station, including roughly 9,600 feet of new sewer infrastructure serving the Third Creek/Stamey Road area.

WHAT TO WATCH NEXT

October 19 notice to proceed and documented field construction progress

October 19, 2026 [22] [23]

Completion timing may change. The infrastructure enables growth but does not itself prove specific future development beyond projects with separate approvals.

What remains uncertain

  • Completion timing may change. The infrastructure enables growth but does not itself prove specific future development beyond projects with separate approvals.

What is documented

  • Verified fact

    City project updates report staking and clearing beginning the week of September 14, mobilization planned for October 12, and notice to proceed set for October 19. The City describes the extension as enabling economic development and future commercial and residential growth along the Stamey Road corridor. [22] [23]

    Completion timing may change. The infrastructure enables growth but does not itself prove specific future development beyond projects with separate approvals. Evidence date: October 6, 2026.

Amounts & scale

  • Approximate length: 9,600 feet · estimate [22] [23]

    Roughly 9,600 feet of sewer infrastructure for this extension. Evidence date: October 6, 2026.

  • Responsive bid: $5,957,869 · estimate [22] [23]

    Responsive bid; not characterized as actual expenditure or a complete all-phase project budget. Evidence date: October 6, 2026.

  • State grant: $2,955,000 · funded [22] [23]

    State grant; distinct from the responsive bid. Evidence date: October 6, 2026.

Targets & projected dates

  • Planned mobilization: October 12, 2026 · Agency projection [22] [23]
  • Planned notice to proceed: October 19, 2026 · Agency projection [22] [23]

Sources & evidence

  1. City of Statesville — Third Creek Sewer Extension

    Project source; full document linked. · Source date: not shown · Checked: October 7, 2026

    Publication date is not established here; the source review date is shown separately.

  2. City of Statesville — City Manager October 2026 update to City Council

    Project source; full document linked. · Source date: not shown · Checked: October 7, 2026

    Publication date is not established here; the source review date is shown separately.